Contract Package CA-10
Gandhi Nagar to Sonapur
Project Overview
Contract Package CA-10 covers a significant portion of the Mumbai Metro Line-4 corridor, spanning from Gandhi Nagar to Sonapur with a total length of 6.685 kilometers. This package includes the design and construction of elevated viaduct and 6 elevated stations, representing advanced metro infrastructure development.
The project encompasses six elevated stations: Gandhi Nagar, Naval Housing, Bhandup Mahapalika, Bhandup Metro, Shangrila, and Sonapur. Each station is strategically positioned to serve dense urban areas and provide crucial connectivity for residents and commuters.
With 78% physical progress achieved and a revised project value of ₹814.03 Crores, this package demonstrates excellent project execution. The high billing percentage of 71.13% reflects efficient financial management and timely milestone completion.