Project Overview

This Special Steel Span erection represents one of the most complex engineering achievements in Mumbai Metro Line 4 development. The project involved the installation of a 62.70-meter long Semi-through W Type girder weighing 540 Metric Tonnes, crossing the existing Jogeshwari Vikhroli Link Road flyover at Gandhi Nagar Junction.

The project was completed successfully and safely over 5 weekend nights starting from April 26, 2025, and ending on May 25, 2025. The span crosses at the 2nd level over the existing JVLR flyover, while Mumbai Metro Line 6 crosses at the 3rd level, creating a complex multi-level transportation infrastructure.

Key technical specifications include a girder height of 4.20 meters, fabricated in multiple pieces at a factory in Pune and transported to Tagore Nagar on Eastern Express Highway for assembly. Two temporary trestles, each measuring 13.4m x 7.4m and weighing 61 Metric Tons, were erected for temporary support during installation.

Key Highlights

62.70m Semi-through W Type girder
540 Metric Tonnes total weight
4.20m girder height
Completed in 5 weekend nights
Complex traffic management
Multi-level infrastructure crossing
Fabricated in Pune, assembled on-site
Two 61 MT temporary trestles used

Technical Specifications

Girder Type
Semi-through W Type
Total Length
62.70 meters
Total Weight
540 Metric Tonnes
Girder Height
4.20 meters
Assembly Segments
30m, 17.10m, 15.10m
Temporary Support
2 x 61 MT trestles
Fabrication Location
Pune
Assembly Location
Tagore Nagar, EEH

Machinery & Equipment

1 x 700 MT capacity heavy duty crane
1 x 500 MT capacity heavy duty crane (with standby)
2 sets multi-axle carriers with pullers
2 backup pullers
9 x 40 ton counter weight trailers
2 x 60 ft lifting beam trailers
10 x Hydras/Farana (14/15 & 27 tonne)
5 x Man lifters
6 x EICHER trucks
5 x Escort vehicles
2 x Ambulances

Workforce Deployment

25 Engineers
30 Riggers
60 Skilled & Unskilled Workmen
5 Welders
100 Traffic Wardens

Project Statistics

length
62.70m
weight
540 MT
height
4.20m
duration
5 nights
completion
May 2025
location
Gandhi Nagar Junction

Project Information

Client
MMRDA
Contract Package
CA-10
Completion Date
May 25, 2025
Category